Covidien Office Fit-out
Project Scope of Work:
- Supply, installation, and commissioning VRF air conditioning systems with concealed ducted units to serve office spaces with all associated ventilation ductwork,fittings, thermal insulation & diffusers.
- Supply, installation & commissioning of dedicated split air conditioning system to serve comms room.
- Supply, installation & commissioning of Inergen fire suppression system to serve comms room.
- Supply, installation & commissioning of Mains, Cold & Hot water services to serve canteen areas.
Location: 20on Hatch Street, Dublin Contract Value: €235,000 M/E Consultant: Metec Engineering Main Contractor: Management & Construction Ltd | Start Date: April 2010 Completion Date: June 2010 Project Manager: Barry Kennedy Peak Manpower: 9 Method of Procurement: Tender Reference Name: Mr. Bernard Denver |